Electrical Engineering

2000Kva Amorphous Core Transformer Install

  • MV to LV Transformer Upgrade.
  • Disconnection and removal of existing on site 1500Kva Transformer.
  • Supply, installation and commission of 2000Kva Super Low Loss Amorphous Core Transformer.
  • Discrimination study and protection design
    • Fault level study of new system from NIE point of supply.
    • Production of protection settings for the MV and LV relays.
    • Documentation of study including protection grading curves and narrative report.
  •  LV Switchboard
    • Installation of upgraded LV Cabling using 500mm Sq. AWA’s 3 per Phase.
    • Fitting all required ladder.
  • Installation and termination of all 12Kv rated single core steel wired armoured cabling.
  • Supply of all onsite crane and forklift hire for the completion of all electrical works on site.
  • Complete design of entire project to include all electrical aspects as detailed above including civil works design for new MV equipment and services, liaising with client to adhere to strict deadline for completion of works.
  • Contract Duration – Main Changeover Shutdown completed in 7 Hours, 4 hours ahead of schedule.

Project Details

Date:

June 28 2019