Electrical design and installation of new plastic separator plant. This consisted of a 5 month contract in which JJ Loughran where responsible for the Design and build of all main control panels and interfaces, consisting of Allen bradley PLC’s & 10 INCH HMI Touch controls. We were also responsible for all electrical engineering aspects which included Electrical ladder & tray containment, Power & Control cabling Installation, Mains cabling, Lighting, Mains Power Boards (1200 Amp LV Form 4 Power Assemblies) and final plant commissioning ahead of schedule.
We were also responsible for Specification and build of all motor and gearboxes for complete plant.
Contract Duration – 4 Months
Project Details
Date:February 9 2016
Category:
Electrical Engineering